Removing and installing air duct for defroster vent
Coolant circuitBleeding hydraulic system following standard procedure
Note
Bleeding the hydraulic system using brake filling and
bleeding equipment -VAS 5234- is described.
A pre-pressure of 2 bar is required for bleeding the ABS
hydraulic unit -N55-.
Specia ...
Removing and installing covers for auxiliary heater control unit -J364
Removing
–
Switch off electrical consumers.
–
Switch off auxiliary and supplementary heater and switch off
ignition.
–
Remove auxiliary heater
→  ...
Connecting air conditioner service station for measuring and checking
Depending on the type of equipment chosen, there may be
variations in the required procedure; therefore always follow
the user's manual for the equipment being used.
Note
Always follow the procedure described in the user's manua ...